The IPHWR-220 (Indian Pressurized Heavy Water Reactor-220) is an Indian pressurized heavy-water reactor designed by the Bhabha Atomic Research Centre.[1] It is a Generation II reactor developed from earlier CANDU based RAPS-1 and RAPS-2 reactors built at Rawatbhata, Rajasthan. It can generate 220 MW of electricity. Currently, there are 14 units operational at various locations in India. It is being used as a base for designing the Bharat small modular reactor (BSMR), for captive use by companies.[2]

The IPHWR design was later expanded into 540 MW and 700 MW designs, as well as the AHWR-300 design.

Reactor fleet

IPHWR-220 Reactor fleet
Power station Location Operation start Status
MAPS-1 Kalpakkam, Tamil Nadu 27 January 1984 Operational
MAPS-2 21 March 1986
NAPS-1 Narora, Uttar Pradesh 1 January 1991
NAPS-2 1 July 1992
KAPS-1 Kakrapar, Gujarat 6 May 1993
KAPS-2 1 September 1995
RAPS-3 Rawatbhata, Rajasthan 1 June 2000
RAPS-4 23 December 2000
RAPS-5 4 February 2010
RAPS-6 31 March 2010
KGS-1 Kaiga, Karnataka 6 November 2000
KGS-2 6 May 2000
KGS-3 6 May 2007
KGS-4 27 November 2010

Technical specifications

Specifications IPHWR-220[3] IPHWR-540[4][5][6][7] IPHWR-700[8]
Thermal output, MWth 754.5 1730 2166
Active power, MWe 220 540 700
Efficiency, net % 27.8 28.08 29.08
Coolant temperature, °C: ?
     core coolant inlet 249 266
     core coolant outlet 293.4 310
Primary coolant material Heavy Water
Secondary coolant material Light Water
Moderator material Heavy Water
Reactor operating pressure, kg/cm2 (g) 87 100
Active core height, cm 508.5 594 594
Equivalent core diameter, cm 451 - 638.4
Average fuel power density 9.24 KW/KgU 235 MW/m3
Average core power density, MW/m3 10.13 12.1
Fuel Sintered Natural UO2 pellets
Cladding tube material Zircaloy-2 Zircaloy-4
Fuel assemblies 3672 5096 4704 fuel bundles in 392 channels
Number of fuel rods in assembly 19 elements in 3 rings 37 37 elements in 4 rings
Enrichment of reload fuel 0.7% U-235
Fuel cycle length, Months 24 12
Average fuel burnup, MW · day / ton 6700 7500 7050
Control rods SS/Co Cadmium/SS
Neutron absorber Boric Anhydride Boron
Residual heat removal system Active: Shutdown cooling system

Passive: Natural circulation through steam generators

Active: Shutdown cooling system

Passive: Natural circulation through steam generators

and Passive Decay heat removal system

Safety injection system Emergency core cooling system

See also

References

  1. ANU SHAKTI: Atomic Energy In India. BARC. Retrieved 2021-03-20.
  2. https://www.world-nuclear-news.org/articles/deadline-extended-to-allow-wider-participation-in-indian-small-reactor-rfp
  3. Status report 74 - Indian 220 MWe PHWR (IPHWR-220). International Automic Energy Agency(2011-04-04). Retrieved 2021-03-21.
  4. Fuel technology evolution for Indian PHWRs. International Atomic Energy Agency.
  5. Design, Safety and Operability performances of 220 MWe, 540 MWe and 700 MWe PHWRs in India. Inter-Regional Workshop on Advanced Nuclear Reactor Technology for Near-term Deployment({Template:Date).
  6. The Indian PHWR. Nuclear Engineering and Design({Template:Date).
  7. Physics design and Safety assessment of 540 MWe PHWR. BARC Newsletter({Template:Date).
  8. Status report 105 - Indian 700 MWe PHWR (IPHWR-700). International Atomic Energy Agency(2011-08-01). Retrieved 2021-03-20.