Template:Infobox public transit The Chennai Mass Rapid Transit System, commonly referred to as Chennai MRTS, is a metropolitan rail transit system in Chennai, India. It is operated by Southern Railway of the state-owned Indian Railways. Opened in 1995, it was the first elevated railway line in India. The railway line runs from Chennai Beach to St. Thomas Mount, covering a distance of Template:Cvt with 21 stations and is integrated with the wider Chennai suburban railway network.
While the suburban railway has been operational in Chennai since 1931, the Planning Commission of Government of India formed a research group to recommend development of transportation in major cities including Madras in 1965. The Madras Area Transportation Study Unit identified eight transport corridors including the Template:Cvt north–southeastern rail corridor along the Buckingham Canal. The Government of India approved a Mass Rapid Transit System for the southern section in 1983–84 with the project to be implemented in four phases. The project was implemented by the Ministry of Railways and construction began in 1991. The first phase from Chennai Beach to Chepauk was completed in 1995 with further extension to Thirumayilai in 1997. Part of second phase from Thirumayilai to Thiruvanmiyur was completed in 2004 with further extension to Velachery in 2007. The planned extension from Velachery to St. Thomas Mount was completed in March 2026, after repeated delays.
The Chennai MRTS line is largely elevated with at-grade sections at its terminals. The line runs at-grade initially till Park Town, parallel to the suburban railway network. It becomes elevated thereon, roughly following the course of the Buckingham Canal and running parallel to the Coromandel Coast till Thiruvanmiyur before deviating west towards Velachery. It uses the same broad gauge (5 ft 6in) as the suburban system, thus allowing the movements of trains between the existing suburban lines and the MRTS. The Chennai MRTS uses 9-car electrical multiple unit (EMU) train sets. The trains use 25 kV overhead catenary for traction. The coaches are manufactured by the Integral Coach Factory, Chennai. The coaches are not air-conditioned and are equipped with first-class and second-class passenger seating.
Template:As of, the system has a daily ridership of 100,000. With the implementation of the Chennai Metro Rail starting in 2015 and planned expansion of the same, further expansion of the MRTS system was put on hold in 2017, with the plans for the MRTS system to be taken over by Chennai Metro Rail Limited. In 2022, the Southern Railway of Indian Railways gave an in-principle approval for the take-over under which the coaches, stations and other infrastructure will be upgraded on par with the Chennai Metro.
Background
The Chennai Suburban Railway started operations in 1931 on a single electrified line from Chennai Beach to Tambaram. Suburban services commenced on the second line between Chennai Central and Gummidipoondi in 1985 the third line from Central towards Arakkonam was added later.[1][2] In 1965, the Planning Commission formed a group to study the suitability of the existing transportation network, to ascertain the viability of various ways of transportation and advocate plans for the expansion of transportation in metropolitan cities including Madras.[3][4]
Planning
Surveys were conducted to supplement the existing transport infrastructure in Madras, such as the Madras Area Transportation Study (1968), Integrated Transport Plan (1977) and Madras Route Rationalisation Study (1986).[5] The Madras Area Transportation Study Unit (MATSU) identified eight important transport corridors including the north–southeastern rail corridor connecting Kasturba Nagar and Manali Road. The study suggested the implementation of a rail-based Mass Rapid Transit System (MRTS) on the southern section of the line along the Buckingham Canal, connecting to the existent suburban system.[6] The system was envisaged as a Template:Convert loop line connecting Chennai Beach and Tiruvottiyur.[7]
Since the planned railway line would pass through congested parts of the city, an elevated rail system was selected, to avoid land acquisition problems.[8] The project was intended to be implemented in four phases: Chennai Beach to Thirumayilai, Tirumayilai to St. Thomas Mount, St. Thomas Mount to Villivakkam and Villivakkam to Ennore.[9][10]
Construction and opening
Phase I
The project was sanctioned for implementation by the Ministry of Railways, Government of India in 1983-84.[4][9] After multiple delays, construction began in 1991 and part of the first phase from Chennai Beach to Chepauk was completed in 1995.[6][11] It became operational on 16 November 1995 and was the first operational elevated railway line in India. The line was extended to Thirumayilai in 1997.[6][9] The cost of construction of the first phase between Chennai Beach and Thirumayilai, estimated to be Template:INRconvert, was fully financed by the Government of India.[6] The first phase was projected to serve about 600,000 passengers per day.[10][12]
Phase II
RITES conducted further studies in 1987 and 1994 on the effectiveness of the existing public transport system for the growing population. The studies proposed further expansion of the MRTS line. In 1998, the Railway Board sanctioned Phase II of the project from Thirumayilai to Velachery.[4] Part of the Phase II line from Thirumaylai to Thiruvanmiyur was opened on 26 January 2004.[13] It initially consisted of a single line of track for both forward and return journeys.[14] On 19 November 2007, the network was extended from Thiruvanmiyur to Velachery.[15][16][17] While the state government gave only the required land for the first phase, it contributed two-thirds of the total project cost of Template:INRconvert for the second phase.[4][6][18]
Phase II extension
The construction for the extended second phase of the project connecting Velachery with St. Thomas Mount started in 2008. It was planned at an estimated cost of Template:INRconvert with the central government bearing two-thirds of the cost and the state government bearing the rest.[9][19] The initial planned alignment was altered subsequently and necessitated the demolition of over 70 residential units, which led to protests by the locals.[20][21] In the Government of India's annual Railway Budget of 2012, it was announced that the line would be commissioned in 2013.[22] In October 2012, Chennai Metropolitan Development Authority (CMDA) resumed the land acquisition for the proposed extension after the Madras High Court vacated its earlier stay order on the same.[23][24] While land acquisition was completed for the construction of majority of the line by April 2013, there were further delays in acquiring land for about Template:Cvt of the stretch and the construction of Puzhuthivakkam station.[25] Template:As of, the construction of about Template:Cvt of the proposed extension was complete.[26]
In May 2014, the High Court ruled that compensation be paid as per newly enacted Land Acquisition Act 2013 on the cases filed by the land owners.[26] In March 2016, the Southern Railway stated that the final phase of the MRTS would take at least 18 months after the state government handed over land to Indian Railways and that it had not yet done so.[27] In 2018, further discussion between the CMDA and the land owners on the compensation to be paid for the land acquisition failed.[28][29] Template:As of, the Indian Railways had completed the construction of Adambakkam and Puzhuthivakkam elevated stations, with about Template:Cvt of the line pending for construction.[30] In 2019, the Madras High Court directed the CMDA to pay higher compensation to the land owners.[28] However, the CMDA filed a review petition against the order in the Indian Supreme Court.[31]
The Supreme Court ordered fair compensation for the land owners and directed the CMDA to complete the land acquisition by 8 January 2021.[32] In June 2022, officials announced that the land acquisition for the final stretch would be completed in the next three months.[33] In July 2023, the authorities said that the construction will be completed by the end of the month and the line will be commissioned for use within the end of the year.[34] On 18 January 2024, a concrete girder on the stretch collapsed, which was expected to further delay the opening of the line.[35][36] Multiple revised deadlines to complete the construction of the final phase were not met.[37][38] After the construction was completed, trial runs were conducted in the first week of March 2026.[39] Commercial service began on the extended section from 14 March 2026.[40][41]
Future plans
The third and fourth phases of the MRTS were initially planned to connect St. Thomas Mount with Villivakkam and Villivakkam with Ennore.[10] The plans have been shelved after the lines overlapped with the proposed extension of the Chennai Metro Rail.[42] In early 2024, a feasibility report was submitted to the state government for a new line from Poonamallee and the planned new airport at Parandur. The Template:Cvt line would have 19 stations and is expected to cost Template:INRconvert.[43]
With the Chennai Metro operational since 2015, the Indian Railways proposed for the MRTS system to be taken over by Chennai Metro Rail Limited in 2017.[44] In July 2018, PwC said that the merger would be expensive, costing around Template:INRconvert to replace the train-sets and establish other facilities.[45] On 11 May 2022, the Southern Railway zone of the Indian Railways granted in-principle approval for the takeover.[46] Template:As of, the take over was still pending as the Indian Railway Board had not approved the same.[47]
Infrastructure
Network and lines
The Template:Cvt line from Chennai Beach to St. Thomas Mount is largely elevated, with a few at-grade sections along the line. The line runs at-grade for Template:Cvt from Chennai Beach to Park Town, alongside the suburban railway line.[6][9][42] From the Park Town station, the line becomes elevated and roughly follows the course of the Buckingham Canal, which runs parallel to the Coromandel Coast.[6][9][48] The line remains elevated for the alignment of the second phase up to Perungudi, after which it returns to an at-grade section at the Velachery station, after which the final section of the line from Velachery to St. Thomas Mount is again elevated.[9][42]
| Phase | Length | Route | Stations | Opening Date |
|---|---|---|---|---|
| Phase I-A | Template:Cvt | Chennai BeachTemplate:NdashChepauk | 5 | 16 November 1995 |
| Phase I-B | Template:Cvt | ChepaukTemplate:NdashThirumayilai | 4 | 19 October 1997 |
| Phase II-A | Template:Cvt | ThirumayilaiTemplate:NdashThiruvanmiyur | 6 | 26 January 2004 |
| Phase II-B | Template:Cvt | ThiruvanmiyurTemplate:NdashVelachery | 3 | 19 November 2007 |
| Phase II-B Extension[49] | Template:Cvt | VelacheryTemplate:NdashSt. Thomas Mount | 3 | 14 March 2026[41] |
The route taken by the MRTS line has resulted in the pillars of the elevated section of the railway encroaching the Buckingham Canal. Although the pillars were placed basis the approval of the state government, the government later proposed plans to restore the canal to make it navigable.[50][51][52] However, as the MRTS pillars have reduced the canal width, a section of the canal is not navigable, and the pillars block the flow of rainwater discharge.[50][53][54]
Track
The Chennai MRTS line bears greater resemblance to the suburban railway than a rapid transit line as it uses the same broad gauge (5 ft 6in) as the Chennai Suburban Railway system, allowing the usage of same train-sets across the existing suburban lines and the MRTS.[6][55] Ballastless track is used in the elevated sections between Tirumayilai and St.Thomas Mount stations.[6][56] The trains use 25 kV overhead catenary for traction.[6][57]
Rolling stock
The Chennai MRTS earlier used six-car electrical multiple unit train sets, which was replaced by nine-car train sets in 2021.[58] A nine-car rake typically has three sets of three motor coaches each at the front, the middle and the last with electric motors used to drive the wheels of the train at a stipulated speed.[59] The EMU coaches are manufactured by the Integral Coach Factory in Chennai.[60][61] The coaches are not air-conditioned and are equipped with two-class (first and second class) passenger seating configuration.[62][63][64][65]
Stations
The MRTS line has 21 stations, and the stations are designed to accommodate six and nine-car train rakes.[42][66][67]
The Chennai Beach station, one of the termini, is a hub for several suburban trains. Along with the Chennai Fort station, it offers connectivity to the commercial area of Broadway.[68][69] The Park Town station is located near the Chennai Central station, which is a hub for other suburban lines and for long-distance express trains.[70][71] The St. Thomas Mount station at the southern end of the line, serves as the intersection of various railway networks. The suburban and long-distance express trains ply on the conventional tracks at ground level, the elevated MRTS line is located at the first level, and the Chennai Metro operates at the second level.[72]
Places of interest such as Parthasarathy Temple, Kapaleeshwarar Temple and Mundagakanniamman Koil are located close to the MRTS railway line.[73][74][75] Marina Beach spans along a stretch of the line close to Thiruvallikeni station.[76] The Chepauk station is located close to the M. A. Chidambaram Stadium.[77] The MRTS passes along the Old Mahabalipuram Road (OMR), which also forms part of the information technology corridor where many companies are located.[78][79][80][81]
| # | Station name[66] | Template:Tooltip[42] | Opening[42] | Connections[82] | Layout | ||
|---|---|---|---|---|---|---|---|
| English | Tamil | Transliteration | |||||
| 1 | Chennai Beach | சென்னை கடற்கரை | Cennaī Kadarkarai | 0 | 16 November 1995 | Template:Rint Chennai Beach (South Line) | At-Grade |
| 2 | Chennai Fort | சென்னை கோட்டை | Cennaī Kottai | 1.70 | Template:Rint Chennai Fort (South Line) Template:Rint Broadway bus terminus | ||
| 3 | Chennai Park Town | சென்னை பூங்கா நகர் | Cennaī Poonga Nagar | 2.54 | Template:Ric Chennai Central
Template:Rint Park (South Line) | ||
| 4 | Chintadripet | சிந்தாதிரிப்பேட்டை | Chinthadripettai | 3.43 | Template:Ric Government Estate Template:Rcb | Elevated | |
| 5 | Chepauk | சேப்பாக்கம் | Chepakkam | 5 | rowspan="16" Template:N/a | ||
| 6 | Thiruvallikeni | திருவல்லிக்கேணி | Thiruvallikeni | 5.74 | 19 October 1997 | ||
| 7 | Light House | கலங்கரை விளக்கம் | Kalangarai Vilakkam | 6.95 | |||
| 8 | Mundagakanniamman Koil | முண்டகக்கண்ணியம்மன் கோவில் | Mundagakanniamman Kovil | 7.925 | 14 May 2014[75] | ||
| 9 | Thirumayilai | திருமயிலை | Thirumayilai | 8.66 | 19 October 1997 | ||
| 10 | Mandaveli | மந்தைவெளி | Mandaiveli | 9.699 | 26 January 2004 | ||
| 11 | Greenways Road | பசுமைவழிச் சாலை | Pasumaivazhi Salai | 11.02 | |||
| 12 | Kotturpuram | கோட்டூர்புரம் | Kottoorpuram | 11.892 | |||
| 13 | Kasturba Nagar | கஸ்தூரிபாய் நகர் | Kasturibai Nagar | 12.824 | |||
| 14 | Indira Nagar | இந்திரா நகர் | Indira Nagar | 13.796 | |||
| 15 | Thiruvanmiyur | திருவான்மியூர் | Thiruvanmiyur | 14.655 | |||
| 16 | Taramani | தரமணி | Tharamani | 16.57 | 19 November 2007 | ||
| 17 | Perungudi | பெருங்குடி | Perungudi | 17.713 | At Grade | ||
| 18 | Velachery | வேளச்சேரி | Velachery | 19.34 | |||
| 19 | Puzhuthivakkam | புழுதிவாக்கம் | Pulutivakkam | 21.19 | 14 March 2026[41] | Elevated | |
| 20 | Adambakkam | ஆதம்பாக்கம் | Adambakkam | 22.19 | TBD[83] | ||
| 21 | St. Thomas Mount | பரங்கிமலை | Parangimalai | 23.98 | 14 March 2026[41] | Template:Rint Template:Ric St. Thomas Mount Template:Rcb | |
Indian Railways has made various plans to use the empty space in the MRTS stations.[84] In February 2009, Indian Railway Catering and Tourism Corporation (IRCTC) announced plans to set up food stalls at MRTS stations with the first such stall inaugurated in April 2018 at Thiruvanmiyur station.[85][86][87][88]
MRTS has been criticised by the public for poor maintenance of the stations, lack of inter-modal transport facilities and security issues.[89][90] The director of Chennai Metro called for the various government agencies to work together to improve the connectivity to the stations.[91] The stations often face issues such as seepage of rainwater and no access to clean drinking water.[92][93][94] A 2006 report by the Comptroller and Auditor General of India cited delays in installation of station amenities such as escalators.[95]
In 2012, there was a shortage of the Railway Protection Force personnel at MRTS stations, which raised security concerns.[96] In 2013, to improve the security for the passengers using the network, Indian Railways declared that the MRTS stations would have a single designated entry and exit point as it was difficult for the existing RPF personnel to monitor multiple gates at the same time.[97][98] If the planned takeover by Chennai Metro is completed, the existing line is planned to be upgraded to be compatible with the metro system. Plans to modernise infrastructure include improved facilities at stations and single integrated ticketing system among others.[99]
Operations
The operational route length between Chennai Beach and St.Thomas Mount is Template:Cvt with a journey time of more than 65 minutes one way.[42][100][101] The system handles about 70 trains on weekdays and reduced capacity on Sundays.[102][103] In 2012, Indian Railways made the schedule for the MRTS services available on Google Maps on Android smartphones.[104][105] The trains can be tracked in real time and the users are provided with updates through an automated SMS system.[106]
Fares and ticketing
The minimum fare for a second class is Template:INRconvert.[107] A second class ticket from Beach to St. Thomas Mount is priced at Template:INRconvert.[108] First class tickets cost about five times higher than the second class fare.[109] In addition to one-time tickets, the Southern Railway issues monthly tickets and quarterly season tickets for frequent travelers.[110][111] Short validity tickets are available for tourists.[112][113][114] The tickets can be bought at the railway ticket counters or booked through a mobile application.[115]
Patronage
The ridership of the Chennai MRTS system increased from approximately 9,000 in 2003 to 66,518 passengers per day in 2008.[10][116] When the line was extended up to Velachery in 2007, the daily ridership increased and it saw a three-fold increase in the revenue.[117][118] Template:As of, the daily ridership is about 100,000.[119] Three stations—Beach, Thirumayilai, and Velachery—accounted for nearly 40 percent of the ridership in 2012.[120]
In 2010, the Indian Railways rolled out dedicated trains for women, which saw poor patronage.[121] In 2023, Chennai Unified Metropolitan Transport Authority (CUMTA) introduced new plans to improve last-mile connectivity to the stations.[122] Indian Railways operates special trains on certain occasions to boost revenue. As the route passes close to some popular religious sites, the MRTS operates special trains during popular religious festivals such as the Vaikunta Ekadashi at Parthasarathy Temple in Thiruvallikeni and the Arupathumoovar festival at the Kapaleeshwarar Temple in Thirumayilai.[73][123] Special trains are run when cricket matches are hosted at the M. A. Chidambaram Stadium in Chepauk,[77][124][125] during Kaanum Pongal festival at Marina Beach,[126] and during bus strikes.[127]
As the MRTS system is not fully integrated with other modes of transportation in the city, access to the stations is an issue.[128][129] As per a survey conducted in 2012, the public called for special focus on pedestrian facilities that would provide access to MRTS stations from nearby roads and bus stops, as well as identifying new feeder routes for the network.[130] Post the completion of the under construction extension, the MRTS system will be connected to the Suburban Railway and the Metro. This would enable commuters to access the railway grid of the different operational rail systems and facilitate improved connectivity from the stations on the MRTS network.[131] The proposed extension up to St. Thomas Mount was expected to increase patronage from people working in the IT establishments, residences and other offices located close to the MRTS network,[132][133] and the ridership increased following the opening of the extended section from Velachery to St. Thomas Mount in March 2026, as it provided access to metro and suburban lines.[134]
Finances
In a 10 month period in 2009–10, the MRTS earned a revenue of Template:INRconvert with Template:INRconvert coming from ticketing sales. It had operating expenses of about Template:INRconvert, which translated to net loss of more than Template:INRconvert.[67] Template:As of, the MRTS registered revenues of Template:INRconvert annually. With estimated operational expenses of about Template:INRconvert, the annual loss widened to Template:INRconvert.[122][135] A major contributor to the losses is the revenue deficit due to subsidised cheaper fares offered by the Southern Railway, which runs the service.[107]
See also
References
- ↑ Template:Cite report
- ↑ Template:Cite report
- ↑ Template:Cite report
- ↑ 4.0 4.1 4.2 4.3 Template:Cite report
- ↑ Template:Cite report
- ↑ 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 Template:Cite report
- ↑ Metro Rail may take over MRTS. The Hindu(10 August 2010). Retrieved 19 August 2012.
- ↑ Mass rejected transit system. Business Today(4 April 2010). Retrieved 15 August 2012.
- ↑ 9.0 9.1 9.2 9.3 9.4 9.5 9.6 9.7 Development of MRTS in Chennai. Retrieved 1 December 2023.
- ↑ 10.0 10.1 10.2 10.3 Towards a discussion of support to Urban Transport development in India, March 2005. Retrieved 25 October 2012.
- ↑ MRTS connectivity from Velachery to St Thomas Mount to be ready by March. The Hindu(1 November 2022). Retrieved 1 December 2023.
- ↑ MRTS work in progress. New Indian Express(16 July 1994). Retrieved 18 September 2012.
- ↑ MRTS services extended. Business Line(27 January 2004). Retrieved 29 July 2012.
- ↑ Extended MRTS stretch in Chennai ready for inauguration. Business Line(18 August 2007). Retrieved 18 August 2012.
- ↑ Tiruvanmiyur-Velachery MRTS service opened. Business Line(20 November 2007). Retrieved 21 August 2012.
- ↑ Template:Cite report
- ↑ Evolution of Chennai's Public Transport System, Sreevatsan, Ajai(31 October 2011). Retrieved 29 February 2012.
- ↑ MRTS Phase II: Three steel girders installed across existing tracks. The Times of India(31 October 2023). Retrieved 1 December 2023.
- ↑ Velachery-St Thomas Mount MRTS by 2022-end. The New Indian Express(28 December 2021). Retrieved 16 January 2022.
- ↑ Protest against MRTS corridor realignment. The Hindu(2 October 2010). Retrieved 15 August 2012.
- ↑ Threat of relocation evokes protests as Southern Railway alters MRTS alignment. The Times of India(1 August 2010). Retrieved 15 August 2012.
- ↑ Template:Cite report
- ↑ MRTS upto St. Thomas Mount back on track. The Hindu(16 October 2012). Retrieved 15 December 2012.
- ↑ MRTS extension stopped in its tracks. The Times of India(16 March 2011). Retrieved 21 August 2023.
- ↑ Decks cleared for acquisition of land for Adambakkam station. The Hindu(10 April 2013). Retrieved 19 April 2013.
- ↑ 26.0 26.1 MRTS Phase II Extension Starts Next Month. The New Indian Express(23 May 2014). Retrieved 5 August 2014.
- ↑ The final leg of Mass Rapid Transit System for a distance of 500 metres is not likely to be completed in the near future. The Hindu(27 February 2016).
- ↑ 28.0 28.1 Velachery-St Thomas Mount MRTS by 2022-end. The New Indian Express(29 December 2021). Retrieved 1 June 2024.
- ↑ Land acquisition talks for MRTS link fail again. The Times of India. Retrieved 1 December 2023.
- ↑ After 11-year wait, construction on St Thomas Mount-Adambakkam MRTS stretch in Chennai to begin soon. The Indian Express(13 November 2019). Retrieved 1 June 2024.
- ↑ Chennai MRTS's last stretch to be delayed further as CMDA approaches SC. The News Minute(21 September 2020). Retrieved 7 July 2023.
- ↑ Chennai: Last-mile demolition to acquire land for MRTS extension begins. Times of India(7 January 2021). Retrieved 1 July 2023.
- ↑ Construction of MRTS' final pillar to start in six months, land acquisition nearing end. The Indian Express(24 June 2022). Retrieved 1 June 2024.
- ↑ Construction of Velachery-St. Thomas Mount MRTS stretch will be completed by end of July. The Hindu(13 July 2023). Retrieved 1 June 2024.
- ↑ Concrete girder of bridge collapses at MRTS worksite in Thillai Ganga Nagar. The Hindu(18 January 2024). Retrieved 1 March 2024.
- ↑ Part of bridge falls, rail project delayed again. The Times of India(19 January 2024). Retrieved 1 March 2024.
- ↑ Hope for Chennai MRTS phase-II extension. The Indian Express(31 October 2018). Retrieved 1 June 2024.
- ↑ Mount-Velachery-Beach MRTS misses deadline, again. The Times of India(27 April 2024). Retrieved 1 June 2024.
- ↑ Velachery-St Thomas Mount MRTS line set for to Mar 10 launch. DT Next(6 March 2026). Retrieved 6 March 2026.
- ↑ MRTS service on Mount-Velachery line from Saturday. The New Indian Express(13 March 2026). Retrieved 13 March 2026.
- ↑ 41.0 41.1 41.2 41.3 MRTS train services begin on Velachery-St. Thomas Mount extended section. The Hindu(15 March 2026). Retrieved 15 March 2026.
- ↑ 42.0 42.1 42.2 42.3 42.4 42.5 42.6 42.7 Template:Cite report
- ↑ Parandur-Poonamallee MRTS in Chennai to cost Rs 10k crore. The New Indian Express(5 January 2024). Retrieved 1 June 2024.
- ↑ Chennai Metro-MRTS merger report in six months. The Hindu(29 May 2017). Retrieved 29 May 2017.
- ↑ Metro-MRTS merger likely to be a costly affair. The Hindu(19 July 2018). Retrieved 22 July 2018.
- ↑ MRTS merger with Chennai Metro gets railway's approval. The New Indian Express(15 May 2022). Retrieved 16 May 2022.
- ↑ CMRL's takeover of MRTS yet to make any headway. Daily Thanthi(15 July 2024). Retrieved 15 July 2024.
- ↑ How Buckingham canal could have saved Chennai. The Hindu(27 December 2018). Retrieved 1 December 2023.
- ↑ MRTS-suburban train linking work resumes after long delay. The Hindu(20 February 2021). Retrieved 20 February 2021.
- ↑ 50.0 50.1 Template:Cite report
- ↑ Buckingham canal restoration: WRD submits plan. The New Indian Express(3 October 2023). Retrieved 1 December 2023.
- ↑ River restoration only on paper, a sham on ground. The Times of India(29 August 2003). Retrieved 1 September 2023.
- ↑ Civic infrastructure struggling to be rain-ready. The Hindu(5 November 2016). Retrieved 1 December 2023.
- ↑ Template:Cite report
- ↑ Metro – Urban – Suburban Systems. Retrieved 13 November 2012.
- ↑ Ballast-less tracks the Solution?, Prabhakar, Siddharth(19 February 2015). Retrieved 1 September 2023.
- ↑ General Description of Electrical Rolling Stock. Retrieved 15 September 2012.
- ↑ MRTS goes full nine-car. The Hindu. Retrieved 1 December 2023.
- ↑ Template:Cite report
- ↑ Fort station to be MRTS hub post CMRL merger. The Times of India(1 April 2017). Retrieved 1 June 2024.
- ↑ Integral Coach Factory. Retrieved 1 December 2023.
- ↑ Why no AC train for Chennai MRTS?. The Hindu(27 February 2013). Retrieved 19 April 2013.
- ↑ Chennai Metro Rail Limited to assess if suburban trains can have AC coaches. The Times of India(11 October 2022). Retrieved 1 December 2023.
- ↑ A first class conundrum for MRTS ticket checkers. The Hindu(29 December 2015). Retrieved 1 December 2023.
- ↑ Plan to launch AC coaches on Chennai suburban trains a non-starter. The Times of India(17 October 2021). Retrieved 1 August 2023.
- ↑ 66.0 66.1 Indian Railways Time Table. Retrieved 31 March 2024.
- ↑ 67.0 67.1 Can Chennai's Mass Rapid Transit System revive itself?. Business Today(16 March 2010). Retrieved 1 December 2023.
- ↑ Beach station awaits makeover as Metro plans MRTS takeover. The New Indian Express(26 September 2017). Retrieved 1 December 2023.
- ↑ Chennai: 21-storey building, skywalk part of Broadway bus terminal. The Times of India(24 February 2022). Retrieved 1 December 2023.
- ↑ Central to Park station, an ordeal. The Times of India(11 March 2023). Retrieved 1 December 2023.
- ↑ Eight biggest railway stations in India. Daily news and analysis. Retrieved 1 December 2023.
- ↑ Integrated station at St. Thomas Mount planned. The Hindu(13 April 2010). Retrieved 18 August 2012.
- ↑ 73.0 73.1 Huge crowds throng temples on Vaikunta Ekadasi. The Times of India(18 December 2010). Retrieved 1 August 2023.
- ↑ Temples on metro route strike gold. The Times of India(8 March 2012). Retrieved 1 June 2024.
- ↑ 75.0 75.1 Mylapore Locals Get a New Stop. The New Indian Express(15 May 2014). Retrieved 1 December 2023.
- ↑ IIT Madras to study upgrade of two MRTS stations. The Times of India(27 January 2024). Retrieved 1 March 2024.
- ↑ 77.0 77.1 Southern Railway to run special MRTS trains. The Times of India(21 March 2024). Retrieved 31 March 2024.
- ↑ MRTS upto St. Thomas Mount back on track. The Hindu(16 October 2012). Retrieved 1 December 2023.
- ↑ U-shaped flyover on OMR to be completed by May end. The Hindu(13 April 2023). Retrieved 1 December 2023.
- ↑ Template:Cite report
- ↑ BRTS: One solution for two problems on OMR. The Times of India(3 November 2023). Retrieved 1 December 2023.
- ↑ Chennai metro map. Retrieved 1 December 2023.
- ↑ Chennai: MRTS train to skip Adambakkam station for now. DT Next(13 March 2026). Retrieved 15 March 2026.
- ↑ Amma canteens may soon come up at Chennai's MRTS stations. The Hindu(5 October 2013). Retrieved 1 December 2023.
- ↑ Snazzy food stalls at MRTS stations. Times of India(27 February 2009). Retrieved 1 December 2023.
- ↑ IRCTC to build food kiosks at MRTS stations off-track. The Times of India(30 March 2012). Retrieved 1 December 2023.
- ↑ Missed a meal? Grab a bite at MRTS station in Chennai. The Hindu(28 September 2013). Retrieved 1 December 2023.
- ↑ IRCTC opens 1st food plaza at Thiruvanmiyur MRTS station. The Times of India. Retrieved 1 December 2023.
- ↑ Lack of safety measures turn incomplete MRTS stations into death trap. The Times of India(1 February 2011). Retrieved 1 August 2023.
- ↑ Badly maintained stations hamper optimum patronage. The Times of India(25 December 2009). Retrieved 1 August 2023.
- ↑ Need to integrate MRTS with other public transport systems. Business Line(25 February 2011). Retrieved 21 August 2023.
- ↑ Rain leak leaves MRTS stations in mess. The Times of India(14 November 2008). Retrieved 1 June 2024.
- ↑ MRTS stations in terrible state after rain. The Times of India(11 November 2009). Retrieved 1 June 2024.
- ↑ How safe is drinking water at train terminals ?. The Hindu(14 July 2011). Retrieved 21 August 2012.
- ↑ Planning, execution and operation of Mass 1Rapid Transit System, Chennai. Chapter III. Retrieved 1 September 2023.
- ↑ Railway cops shortage hits security at MRTS stations. The Hindu(6 December 2012). Retrieved 6 December 2012.
- ↑ MRTS stations to have 1 entry, exit. The Hindu(5 January 2013). Retrieved 5 January 2013.
- ↑ Template:Cite report
- ↑ Chennai Metro rail likely to take over MRTS. Times of India. Retrieved 5 August 2014.
- ↑ Operational time of MRTS trains revised. The Hindu(1 July 2012). Retrieved 21 August 2012.
- ↑ Technical snag delays MRTS services. The Hindu(18 March 2012). Retrieved 21 August 2012.
- ↑ Template:Cite report
- ↑ Template:Cite report
- ↑ Google simplifies public transit information. The Hindu(19 August 2012). Retrieved 20 August 2012.
- ↑ Mass Rapid Transit System, Metro path map is now part of mobile app. The Times of India(20 August 2012). Retrieved 1 August 2023.
- ↑ Track MRTS trains through SMS. The New Indian Express(18 February 2012). Retrieved 1 August 2023.
- ↑ 107.0 107.1 MRTS fare hike in the offing as Tamil Nadu govt prepares for takeover. The New Indian Express(5 May 2023). Retrieved 1 December 2023.
- ↑ Chennai: Post-Metro merger, MRTS fares may go up by five to seven times. The New Indian Express(20 January 2018). Retrieved 1 December 2023.
- ↑ First-class MRTS commuters complain of shoddy facilities. The Times of India(12 December 2018). Retrieved 1 December 2023.
- ↑ Template:Cite report
- ↑ Wait for ticket gets painful. The Hindu(8 May 2012). Retrieved 21 August 2012.
- ↑ Template:Cite press release
- ↑ Template:Cite report
- ↑ Southern Railway introduces tourist tickets in Chennai suburban areas. The New Indian Express(25 December 2019). Retrieved 1 June 2024.
- ↑ Buy suburban train tickets via app. The Hindu(1 February 2021). Retrieved 1 December 2023.
- ↑ MRTS getting popular, yet it has miles to go. The Hindu(11 November 2008). Retrieved 15 August 2012.
- ↑ Template:Cite report
- ↑ 20 years on, a favourite with commuters. The Hindu. Retrieved 1 December 2023.
- ↑ Cite error: Invalid
<ref>tag; no text was provided for refs namedRider - ↑ Swanky new road, but MTC buses shy away. The Hindu(17 January 2012). Retrieved 21 August 2012.
- ↑ Poor patronage for MRTS Ladies Special service. The Hindu(24 February 2010). Retrieved 1 August 2023.
- ↑ 122.0 122.1 CUMTA to promote last mile connectivity at 18 stations. The Times of India(15 September 2023). Retrieved 1 December 2023.
- ↑ Template:Cite press release
- ↑ Special trains for cricket match. The Hindu(19 March 2011). Retrieved 18 August 2012.
- ↑ Template:Cite press release
- ↑ Thousands throng Marina for Kaanum Pongal. One India News(17 January 2008). Retrieved 18 August 2012.
- ↑ Commuters stranded across Tamil Nadu as bus strike enters 4th day. The Economic Times(7 January 2018). Retrieved 1 August 2023.
- ↑ Review of First Master Plan, Chapter 1. Retrieved 19 August 2012.
- ↑ Not all together here. The Hindu(23 September 2013). Retrieved 14 October 2013.
- ↑ Survey to identify lacunae in facilities near MRTS stations. The Hindu(19 October 2012). Retrieved 20 October 2012.
- ↑ Last mile MRTS link likely to redefine train travel in city. The Times of India(15 March 2012). Retrieved 15 August 2023.
- ↑ Velachery-St Thomas Mount MRTS link, boon for biz units. Business Line(16 March 2012). Retrieved 21 August 2012.
- ↑ Three avatars of rail services under one house. The Times of India. Retrieved 1 December 2023.
- ↑ Chennai MRTS ridership jumps after St Thomas Mount–Velachery extension. The Economic Times(22 March 2026). Retrieved 22 March 2026.
- ↑ MRTS upto St. Thomas Mount back on track. The Hindu(16 October 2012). Retrieved 16 October 2012.